Extreme Makeover Tennessee Build Timeline
-By sunset on Sunday, the site was prepped
-By sunrise Monday, July 31st, the foundation was poured and pool area prepped
-By sunset on Monday the house was framed and fiberglass pool installed
-By midnight on Monday, infrastructure systems were roughed in (electrical, plumbing, heating/air, etc) and roofing was completed; doors and windows installed
-By sunrise on Tuesday, August 1st, drywall was hung and dressed
-By midday on Tuesday, the bricking was finished
-By sunset on Tuesday, interior walls were sanded and primed and ready to paint
-By sunrise on Wednesday, August 2nd, the driveway was poured, front yard trees planted, and the pool decking poured
-By midday on Wednesday, base coat paint was complete, flooring, cabinet, tile and fixture installation began
-By midnight on Wednesday, flooring was near completion; cabinet, tile and fixture installation was largely complete; yard grading for landscaping and interior trim woodwork began Sunday noon, July 30th: Ground was broken
-By sunrise on Thursday, August 3rd, lighting fixtures, gutters, and electrical trip was largely complete; yard grading was near completion, as the interior trim work
-By midday on Thursday, the interior of the Hawkins home was substantially complete, and Capital Homes turned the house keys over to Extreme Makeover design team for furnishing and embellishment. Work on landscaping and back yard features continued into Thursday evening
-By sunrise on Friday, all exterior work was substantially complete, and the Hawkins home was ready to present to Jerrod, Amy, Jair and Cole.
Article Written & Submitted by Nora Mayor